Bettercoal Producer
Drummond
Country of operation: Colombia
Site assessed against the Bettercoal Code: 2019
Continuous Improvement Plan agreed: 2019
Public report
Read the overview
Continuous Improvement Plan (CIP) progress
Progress in working towards meeting the provisions of the Bettercoal Code.
Continuous Improvement Plan commencement: April 2019
Figures accurate as of: Sept 2023
CIP progress
NOV
2022
30
Total assessment findings / changes to be implemented.
28
Changes implemented and independently verified.
1
Changes implemented and awaiting on-site verification.
1
Findings Open/ changes still to be implemented.
Timeline
Oct 2018
LETTER OF COMMITMENT & ASSESSMENT PLANNING
Signed letter of commitment to work towards meeting the expectations of the Bettercoal Code. Completed questionnaire to allow independent assessors to plan for on-site assessment.
Jan 2019
ON-SITE ASSESSMENT
On-site mine assessment carried out, assessing site(s) against the provisions of the Bettercoal Code.
April 2019
CONTINUOUS IMPROVEMENT PLAN AGREED
Continuous Improvement Plan (CIP) set. The CIP supports the company in working towards meeting the expectations of the Bettercoal Code.
2019-2022
Implements changes according to continuous improvement plan
Evidence of changes implemented to better align operations with the Bettercoal Code are submitted regularly and verified by independent assessors.
Aug 2022
CIP Site verification visit
Assessment team completes on-site CIP monitoring visit to verify practices to address the
findings which are still open in their CIP and require on-site visit to verify implementation.